Elizabeth North Project Update

March 2021

Probuild in conjunction with client PDG Corporation are well underway on site at Elizabeth North.

Currently on site at Elizabeth North Stage 1, the core system has reached its full height and has been dismantled. The team has had a successful top out of structure at level 9 on the 25th Feb and are in preparation for the Stage 1 screens to be removed to allow for the completion of façade activities. The façade system for Stage 1 has arrived in Australia and façade works have begun on levels 3 and 4.

Once complete, Stage 1 Shellworks will continue to progress up the building and fit out works for the Toyota Tenancy on Levels B2-2 will commence.