probuild-banner-template-(Convention Centre Darling Habour)

Convention Centre Darling Harbour Fitout

An eight week, fast-tracked fitout of function rooms and lobbies valued at $5.9 million. The 3800m² project involved demolition, strip-out , refurbishment, operable walls, services and audio visual upgrades.
Probuild delivered the project with a tight timeframe whilst the centre was closed for Christmas.
The project was completed in February 2011.

CLIENT

Sydney Harbour Foreshore Authority (SHFA)

COMPLETED

February 2011

ARCHITECT

Cox Richardson